Use the information in the table and sequence the six jobs using the slack per remaining operation algorithm
Calculate the average flow times and average lateness. All jobs arrived at time zero and are ready at time zero.
Job Production Time Due Date
A 10 20
B 15 25
C 17 22
D 20 31
E 16 20
F 20 24
Job Date Received Prod Time Due Date Slack Slack per operation Order Flow time Late
A 0 10 20 10 3.33 fifth 83 63
B 0 15 25 10 5 sixth 98 73
C 0 17 22 5 1.67 third 53 31
D 0 20 31 11 2.75 fourth 73 42
E 0 16 20 4 1.33 first 16 0
F 0 20 24 4 1.33 second 36 12
TOTAL 98 359 221
AVERAGE 59.83 36.83
Average Flow Time = 59.83
Average Past Due = 36.83
You might also like to view...
Which of the following terms is NOT typically found in a shareholder's agreement? Terms
A) conferring a right of first refusal to existing shareholders to buy the shares of other shareholders before outsiders can purchase the shares B) that determine the value of shares C) that each shareholder will be on the board of directors D) that outline the rights to buy shares if there are dissident shareholders E) all of the above are typically found in shareholders agreements.
Discounts tend to be the higher for domestic vehicles due to perceived declining quality and resale value than for imports
Indicate whether the statement is true or false