A part of the project management plan that is the baseline of the scope of a project and includes the project scope document, WBS, and WBS dictionary best defines
A) network diagram.
B) definitive schedule.
C) WBS.
D) scope baseline.
D
Business
You might also like to view...
When implementing new enterprise systems in a company, process issues that may arise can be effectively resolved by ________
A) encouraging entities at different organizational levels to create separate information systems B) developing committees and steering groups for process management C) bringing conciliators or arbitrators into the company to sort the issues D) giving the responsibility of resolving issues to the company's CEO