Determining cost and schedule reserves, identifying risks requiring the most attention, and determining the overall project risk exposure are all part of the process of Perform Qualitative Risk Analysis, Perform Qunatitative Risk Analysis, and:

A. Identify Risks.
B. Plan Risk Responses.
C. Control Risks.
D. Plan Risk Management.

Answer: B. Plan Risk Responses.