A project consists of four activities with information as shown in the table. What is the overall variance of the project?

Activity Predecessor Length Standard Deviation
A -- 10 2
B A 12 1
C B 16 2
D C 14 3

A) 18
B) 8
C) 2.82
D) 5.56

A