To avoid negative values, it is best to use a bounded type of distribution for project estimating because it has limiting values (i.e. values that cannot exceed certain boundaries). Of the following, a ______ distribution type isn’t considered a bounded distribution.

A. beta
B. triangle
C. uniform
D. normal

D. normal