Which of the following statements regarding CPM networks is true?

A) There can be multiple critical paths on the same project, all with different durations.
B) The early finish of an activity is the latest early start of all preceding activities.
C) The late start of an activity is its late finish plus its duration.
D) If a specific project has multiple critical paths, all of them will have the same duration.
E) None of the above are true.

D

Business

You might also like to view...

Betty is beneficiary of a $15,000 deed of trust on a single-family home located in Long Beach, California. Trustor Milo made $2,000 in payments, then defaulted. At a trustee's sale, the property sold for $10,000, resulting in a $3,000 deficiency. In California, a deficiency judgment cannot be obtained:

A: If the security is a purchase-money trust deed; B: If remedy of trustee's sale is used; C: If fair market value of the property exceeds the amount due on the trust deed; D: In any of the above situations.

Business

Business in the Middle East is primarily driven by the price of steel

Indicate whether the statement is true or false

Business