Determine the critical path

Consider the following project.

Activity Immediate Processor Activity Time (days)
A - 6
B - 8
C A, B 5
D B 4
E C 7
F C, D 3
G D 6
H E, F, G 5

A) ACEH
B) BCEH
C) BDFH
D) BDGH

Answer: B