Describe resource leveling; its objectives and the basic five-step technique to perform it

What will be an ideal response?

Resource leveling is the process that addresses the complex challenges of project constraints. With resource leveling we are required to develop procedures that minimize the effects of resource demands across the project's life cycle. Resource leveling has two objectives: to determine the resource requirements so that they will be available at the right time, and to allow each activity to be scheduled with the smoothest possible transition across usage levels.
The basic steps necessary to produce a resource-leveled project schedule include the following:
Create a project activity network diagram.
From this diagram, create a table showing the resources required for each activity, the activity durations, and total float available.
Develop a time-phased resource loading table that shows the resources required to complete each activity, the activity early starts, and late finish times.
Identify any resource conflicts and begin to smooth the loading table using one or more of the heuristics for prioritizing resource assignment across activities.
Repeat the fourth step as often as necessary to eliminate the source of resource conflicts.

Business

You might also like to view...

Despite a number of embarrassing events during his administration, President Bill Clinton remained quite popular because he ________

A) had a professorial manner B) displayed confidence by uttering, "You betcha!" C) like Joe/Jane Six Pack, he was able to grasp issues easily D) had an easygoing, "just folks" demeanor

Business

If interest rates are positive, then discounting increases the future value of an investment while compounding reduces the present value of an investment

Indicate whether the statement is true or false.

Business