What is aggregated buffer and how can the appropriate amount be determined?

What will be an ideal response?

Aggregated, or project, buffer is a consequence of the critical chain approach to project scheduling. Critical chain project management cuts activity length estimates in half and creates an overall aggregate buffer for the project manager to apply to the entire project as needed. Determination of the project buffer can be accomplished two different ways — the quick-and-dirty Goldratt technique that calls for retention of 50% of the total project buffer or a mathematically derived method suggested by Newbold, given by the equation:

Buffer = ? =

Business

You might also like to view...

Two years into a ten-year lease, the lessor and lessee agree to terminate the rental agreement, with the lessee vacating the property and the lessor not demanding any further payment of rent. This is known as:

A: Reformation; B: Release; C: Surrender; D: Constructive eviction.

Business

Public sector unions are required to obtain written consent from nonmembers they represent in a bargaining unit before spending fees collected from them for electioneering expenses

Indicate whether the statement is true or false

Business