Refer to the scenario above. Which of these statements is BEST?

A) Only four of these activities have zero slack.
B) The late finish of D minus the late finish of C is less than the slack of B.
C) B's latest start plus its slack equals F's late finish.
D) The sum of the latest start times for activities A through E is less than the sum of the latest start times for F and G.

Answer: D