The following table contains a list of activities, with early- and late-start and finish times and crash costs for the network shown in the figure. All start and finish times and crash costs are on a per-week basis

Each activity can be reduced by one week at the most.
a. Determine the uncrashed activity lengths for activities A though K.
b. Determine the minimum completion cost for this project if each week carries a fixed cost of $1,000.

Activity ES EF LS LF Crash Cost/week
A 0 5 0 5 $1,100
B 5 9 13 17 $250
C 5 11 5 11 $1,200
D 0 6 1 7 $350
E 6 10 7 11 $900
F 9 14 17 22 $875
G 11 17 16 22 $1,500
H 11 18 11 18 $500
I 18 26 18 26 $300
J 17 21 22 26 $625
K 26 34 26 34 $750

Activity lengths for A—K can be found by subtracting the early start of each activity from the late start of each activity.

The activity lengths appear in this table:
a.
Activity Length LS LF Crash Cost/week
A 5 0 5 $1,100
B 4 13 17 $250
C 6 5 11 $1,200
D 6 1 7 $350
E 4 7 11 $900
F 5 17 22 $875
G 6 16 22 $1,500
H 7 11 18 $500
I 8 18 26 $300
J 4 22 26 $625
K 8 26 34 $750

b.
The critical path is ACHIK = 34 weeks. Other paths are DEHIK = 33; ACGJK = 29; DEGJK = 28; and ABFJK = 26. With a fixed cost of $1,000/week, the initial cost is 34 weeks @ $1,000 = $34,000.
The cheapest critical-path activity is I @ $300, so reducing I from 8 weeks to 7 weeks costs $300 but saves $1,000, resulting in a net savings of $700.
The next cheapest critical-path activity is H @ $500, so reducing H from 7 weeks to 6 weeks costs $500 but saves $1,000, for a net savings of $500.
The next cheapest critical-path activity is K @ $750, so reducing K from 8 weeks to 7 weeks costs $750 but saves $1,000, for a net savings of $250.
The other two activities on the critical path are more expensive to crash than the penalty cost, so the cheapest completion time is 34 weeks - 3 weeks (I, H, K) = 31 weeks for a cost of $31,000 plus the crash costs of $300 + $500 + $750 = $32,550.

Business

You might also like to view...

Point sources are sources of pollution that are fixed and stationary

Indicate whether the statement is true or false

Business

Use the information in Figure 5.1. What is the capacity for the A-B-D-E process route?

A) 10 students per hour B) 6 student per hour C) 3.5 students per hour D) 2.9 students per hour

Business