Match the following terms to their meanings:

I. Finish date
II. Start date
III. Current date
IV. Status date
V. Project Information dialog box

A. Used to calculate the start date
B. Determined by your computer's clock
C. Used to update various aspects of a project
D. The default date setting in Project 2013
E. The date you set to run reports on a project's progress

A, D, B, E, C