________ scheduling in Project 2013 is where the duration of a task is shortened as resources are added or lengthened as resources are removed from a task
A) WBS B) Effort-driven C) Subtask D) Resource-driven
B
Computer Science & Information Technology
You might also like to view...
The procedures that an object performs are known as the object's __________.
a. records b. methods c. addresses d. fields
Computer Science & Information Technology
Which range of SQL Server error message severity levels are user-generated messages that must be fixed by the user?
A. 1-10 B. 11-16 C. 17-10 D. 20-25
Computer Science & Information Technology