Which termination clause allows an organization to end the outsourcing agreement and go to court to collect compensation for the damages caused?

a. Termination for convenience
b. Termination for financial crises
c. Termination for failure to meet service and performance levels
d. Termination for material breach of contract

d. Termination for material breach of contract
A material breach of contract is a failure to perform that strikes so deeply at the heart of the contract that it renders the agreement irreparably broken and defeats the purpose of making the contract in the first place. If a material breach occurs, the other party can simply end the agreement and go to court to try to collect damages caused by the breach.

Computer Science & Information Technology

You might also like to view...

Name two ways to split an existing path

What will be an ideal response?

Computer Science & Information Technology

Exposurefactor is the expected percentage of loss that would occur from a particular attack. _________________________

Answer the following statement true (T) or false (F)

Computer Science & Information Technology