Define learning curve theory and describe how learning curves are used in project management

What will be an ideal response?

Learning curve theory says that a task can be performed more quickly as repetitions increase, specifically a doubling of output results in a fixed percentage reduction in time required to complete the last unit produced. Learning curve rates can be used in a project if there is an activity that remains fairly constant and is performed repeatedly. Rather than using a direct multiplier of the number of repetitions times the time required to complete the first iteration, the project manager can use the learning curve equation
Yx = aXb
to calculate the time required for successive units as long as the learning curve rate can be estimated. The result will be a time estimate lower than by direct multiplication, which might permit the project manager to more accurately gauge the amount of labor and time required and prepare a more competitive bid.

Business

You might also like to view...

In a high-performance work system, organizational structure promotes cooperation, learning, and _____.

A. traditional management practices B. personal discipline C. improved financial performance D. continuous improvement E. productivity in all levels of the organization

Business

_____ is a logical process that involves evaluating the effectiveness of a message in relation to the needs of the audience and the purpose of the message

A) Drafting B) Evaluating C) Perfecting D) Revising E) Writer's block

Business