What is the cost variance of Project Makeready based on the data in the earned value table shown below?
Activity 7 14 21 28 35 42 49 Plan % Complete
Install fixtures 325 250 575 100%
Refinish floors 550 85 635 100%
Replace doors 350 275 625 100%
Complete tiling 1,200 565 1,765 80%
Install back door 875 225 1,100 70%
Landscaping 200 350 550 25%
Monthly Plan 325 800 435 1,475 1,440 425 350 5,250
Monthly Act 550 550 550 1,100 1,650 550 1,100
A) -$1,896
B) -$1,096
C) -$800
D) -$406
A