Explain the significance that data accuracy can have in cost estimating.

What will be an ideal response?

This answer should be obvious to the student if they understand the concept of
how important cost estimating is in the overall project budget process. Inaccurate
data will establish the BAC incorrectly and will be used as an inaccurate baseline
to track actual costs. The unfortunate reality is that the project might actually be
doing fine cost wise, but will appear off as the baseline is not accurate, and the
project manager will try to make corrections that are not needed.

Computer Science & Information Technology

You might also like to view...

A webpage displays a potentially offensive advertisement on a computer. A customer walking by notices the displayed advertisement and files complaint. Which of the following can BEST reduce the likelihood of this incident occurring again?

A. Clean-desk policies B. Screen-locks C. Pop-up blocker D. Antispyware software

Computer Science & Information Technology

You can print a text-only version of your presentation by selecting Outline in the _____ section.

A. Text-only B. Handouts C. Options D. Settings

Computer Science & Information Technology