What is the late start time for Activity E given the activity times and precedence requirements shown in the table?

Activity Time Predecessor
A 5 --
B 7 --
C 8 A
D 7 A
E 4 B
F 8 C, D
G 9 E, F
H 7 G

A) 14
B) 15
C) 16
D) 17

D

Business

You might also like to view...

Total customer cost consists of only the non-monetary costs in evaluating, obtaining, using, and disposing of the given market offering

Indicate whether the statement is true or false

Business

In a simple random sample, ________

A) every member of the population has a known and equal chance of selection B) the population is divided into mutually exclusive groups (such as blocks), and the researcher draws a sample of the groups to interview C) the researcher selects the easiest population members from which to obtain information D) the population is divided into mutually exclusive groups and random samples are drawn from each group E) the researcher finds and interviews a prescribed number of people in each of several categories

Business