Draw a UML model of the team organization of the OWL project for each the three main phases (i.e., initiation, steady state, termination).

What will be an ideal response?

An example solution to this exercise is depicted in Figure 14-1. During project initiation, the management team is

responsible for the planning and other management activities, while the requirements team defines the system with

the users and the client and the architecture team design a preliminary architecture. During steady state, a team for

each subsystem is created, along with a documentation team and a quality control team. During project termination,

the subsystem teams are replaced with a single installation team which is responsible for deploying the system and

fixing any last minute problems discovered by the quality control team.

Computer Science & Information Technology

You might also like to view...

If a variable uses more than one byte of memory, for pointer purposes its address is

a. the address of the last byte of storage b. the average of all the addresses used to store that variable c. the address of the first byte of storage d. the address of the second byte of storage e. None of these

Computer Science & Information Technology

In the accompanying image of Microsoft PowerPoint 2016, Box A points to the _____.? ?

A. ?Styles gallery B. ?Variants gallery C. ?Themes gallery D. ?Illustrations gallery

Computer Science & Information Technology