A manufacturer needs to produce 300 coffee pots per 8 hour day. The discrete tasks required to produce a coffee pot have been identified, timed in seconds, and ordered as indicated in the table

Sketch the precedence diagram and then assign tasks to workstations on the production line to achieve the required level of output. Break ties by assigning the longest task first. Determine the efficiency delay of your line balance.

Task Time Predecessors
A 80 --
B 25 A
C 35 A
D 20 B, C
E 50 C
F 70 E
G 45 D
H 25 G
I 15 G
J 40 F, H, I
What will be an ideal response?

Answer: The precedence diagram is shown below.

The takt time for 300 units in 8 hours is

takt time = = 96 sec/unit

Station 1 2 3 4 5
Task A C E F B D G H I J Totals
Work 80 35 + 50 70 + 25 20 + 45 + 25 15 + 40 405
Idle 15 10 0 5 40 70

Idle Time = IT = WActual CT -
IT = 5 × 95 - 405 = 70

Efficiency delay = 100% - 100% = 85.3%

Business

You might also like to view...

Roberts Produce Company has fixed costs of $14,000. The company's contribution margin ratio is 46%, and the ratio of selling revenue to sales is 20%. What is the breakeven point in sales dollars? (Round your answer to the nearest dollar.)

A) $70,000 B) $30,435 C) $6,440 D) $2,800

Business

A store has the right to search the bags of a person that they honestly suspect has stolen goods

Indicate whether the statement is true or false

Business