A seven activity project has the activity durations (in weeks) and costs shown in the table. It is possible to speed up every one of the activities by paying a little more. What is the least expensive 30-week project?
Activity Predecessor Normal Duration Normal Cost Crash Duration Crash Cost A -- 7 $2000 5 $3000 B -- 8 $1500 6 $2000 C A 12 $2500 10 $2900 D B 13 $3000 10 $4200 E B 15 $4000 12 $5500 F C, E 10 $3200 8 $4000 G D 7 $1800 6 $2200 A) $18,900 B) $19,200 C) $19,500 D) $19,800