A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table
What is the length of a feeder buffer if this project is managed using critical chain methodology?
Activity Predecessor Length Activity Predecessor Length
A -- 18 E C, D 13
B -- 16 F C 9
C A 22 G E, F 15
D B 14
A) 3.5 days
B) 2.5 days
C) 1.5 days
D) 0.5 days
B