Developing an understanding of the content and complexity of the project is the purpose of:

A) developing a project charter activity of the project planning phase.
B) setting a baseline project plan activity of the project planning phase.
C) determining project standards and procedures activity of the project planning phase.
D) describing the project scope, alternatives, and feasibility activity of the project planning phase.
E) closing down the project activity of the project planning phase.

D
Explanation: D) During the project planning phase the scope, alternative and feasibility of the project are defined.

Business

You might also like to view...

What are six influence strategies for gaining and using power that scholars have identified?

What will be an ideal response?

Business

A quick ratio that is much smaller than the current ratio indicates that

a. inventories represent a large portion of current assets. b. the company has a low inventory turnover. c. inventories represent a small portion of current assets. d. the company has a high inventory turnover.

Business