The quantity variance for direct materials can be computed by multiplying the standard price by the difference between the ________

A) standard inputs allowed and expected inputs allowed at actual output
B) quantity of inputs actually used and the quantity of inputs that should have been used for the expected output
C) standard inputs allowed and expected inputs allowed for expected output
D) quantity of inputs actually used and the quantity of inputs that should have been used for actual output

D

Business

You might also like to view...

If the correlation coefficient is between 0.0 and 0.2, then there is a good chance the null hypothesis will be rejected.

a. true b. false

Business

Marco asks his manager to listen in while he makes calls one day to help him figure out what he could be doing better. The manager concludes that Marco is doing an excellent job of building rapport but is not qualifying prospects as he talks to them

The manager suggests that Marco spend less time talking about the prospect's personal details and: A) more time talking about the features of the product B) focus on non-verbal ways to build rapport with the prospect, such as making active listening noises C) keep a list of qualifying questions in front of him so he makes sure to ask each one of them during the call D) practice his elevator pitch so he can help the prospect understand the product more quickly, since they do not have time on the phone to do a long pitch E) instead, talk about himself so the prospect will be able to trust him more easily

Business