A project has a schedule reserve of 28 days when the customer adds scope not previously planned for. The change has a 40 percent chance of delaying the project by 14 days. What should be done?
A. Add more resources to the project.
B. Add 5.6 days to the schedule reserve.
C. Plan to add 14 days of overtime to the project
D. Look for ways to cut 14 days of work from another activity
Ans: B. Add 5.6 days to the schedule reserve.