Labor cost for set-up is $500/hour. If the plant plans on level material use and operates 50 days per year, determine the time it takes to setup

Annual demand 5000
Daily production 1000
Lot size 700
Annual holding cost per unit $25

S = Q^2 ? H ? (1 - d/p)/(2D) = 700^2 ? 25 ? (1 - 5000/50/1000 )/(2 ? 5000 ) = $1102.5
$1102.5/$500 = 2.205 hours

Business

You might also like to view...

A project consists of four activities with information as shown in the table. What is the overall standard deviation of the project?

Activity Predecessor Length Standard Deviation A -- 10 2 B A 12 1 C B 16 2 D C 14 3 A) 8.00 B) 4.24 C) 2.82 D) 5.56