If a company plans to sell 48,000 units of product but sells 60,000, the most appropriate comparison of the cost data associated with the sales will be by a budget based on
a) 60,000 units of activity.
b) 54,000 units of activity.
c) the original planned level of activity.
d) 48,000 units of activity.
a) 60,000 units of activity.
Business
You might also like to view...
MLOs only must pass a state mortgage exam.
a. true b. false
Business
There are six jobs that are awaiting processing at a machining center. The jobs are shown in the table with their processing time and scheduled completion time
Schedule the jobs by earliest due date, shortest processing time and the critical ratio rule and calculate average lateness for all the jobs. Which scheduling technique performs BEST? Job Process Time Due Time A 12 25 B 8 32 C 15 40 D 10 15 E 20 27 F 17 46 What will be an ideal response?