A Methods and Measurements Analyst needs to develop a time standard for a certain task. The task involves use of a ruler, square, and portable electric saw to mark and cut the "notch" in a rafter (a standard carpentry task of home construction)

In a preliminary study, he observed one of his workers performing this task five times. The observations were made in an air-conditioned, well-lit training facility, at ground level, with all tools and equipment clean and readily available.

Observation: 1 2 3 4 5
Task time (seconds): 82 74 80 83 76

a. What is the actual average time for this task?
b. What is the normal time for this task if the employee worked at a 20% faster pace than is typical for adequately trained workers?
c. What is standard time for this task if allowances sum to 14%?
d. If the analyst then thought more carefully about his experiment and decided that the allowances needed to be increased to match the real (outside, not air-conditioned) work environment, and that the proper allowance was not 14% but 20%, what is the revised standard time?

a. Actual average time is 79 seconds.
b. Normal time is (79 )(1.20 ) = 94.8 seconds.
c. Standard time is 94.8 / (1 - .14 ) = 110.23 seconds.
d. The revised standard time is 94.8/(1 - .20 ) = 118.5 seconds.

Business

You might also like to view...

In an REA diagram, resource entities

A) can be linked to event entities in Business Cycle A and to event entities in Business Cycle B. B) cannot be linked to event entities in Business Cycle A and to event entities in Business Cycle B. C) cannot be linked to agent entities. D) none of the above

Business

Which of the following agencies was NOT created by the Occupational Safety and Health Act?

a. The Occupational Safety & Health Administration b. The Occupational Safety & Health Review Commission c. The National Institute of Occupational Safety & Health d. The National Institute of Mental Health

Business