The critical path for the network activities shown below is ________ with duration ________

Activity Duration Immediate
Predecessors
A 10 ---
B 8 ---
C 2 A
D 4 A
E 5 B,C, D

A) A-C; 12
B) A-D-E; 19
C) B-E; 13
D) A-B-C-D-E; 29
E) none of the above

B

Business

You might also like to view...

Which of the following statements about life insurance policy settlement options is NOT correct?

A) Under the fixed-period option, the payment of excess interest will lengthen the payment period. B) Debra and Renee are each receiving monthly income from their deceased spouses' identical life insurance policies under the fixed-period option. Debra's payments are to be made for 15 years and Renee's for 20 years. Debra receives the larger monthly payments. C) By using the interest-only option, 2 or more settlement options can be combined for added flexibility. D) Payments under the interest-only option may be made at a rate higher than the guaranteed minimum."

Business

If a market survey indicates that your firm's sales would be $620,000, what net profit would you expect to earn?

What will be an ideal response?

Business