Refer to the figure. Determine the latest start time (LST) and latest finish time (LFT) of activity B
A) LST = 9, LFT = 5
B) LST = 5, LFT = 9
C) LST = 8, LFT = 4
D) LST = 4, LFT = 8
E) LST = 8, LFT = 10
D