Use the information in the table regarding this seven-month project to calculate the SPI in terms of dollars and compare it with the SPI calculated in terms of time. Perform both calculations for months 1 through 6
Then use the SPI(t) to provide the Estimate at Completion for Time (EACt).
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7
PV ($) $125 $275 $500 $875 $1,485 $2,325 $2,670
EV ($) $150 $320 $510 $850 $1425 $2280 $0
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7
PV ($) $125 $275 $500 $875 $1,485 $2,325 $2,670
EV ($) $150 $320 $510 $850 $1425 $2280 $0
SV ($) $25 $45 $10 -$25 -$60 -$45
SPI ($) 1.20 1.16 1.02 0.97 0.96 0.98
C 1 2 3 3 4 5
ES 1.2 3.3 4.04 3.93 4.90 5.95
SV(t) 0.20 1.3 1.04 -0.67 -0.09 -0.05
SPI(t) 1.20 1.65 1.35 0.98 0.98 0.99
The Estimate at Completion for Time is:
EACt = = = 7.063 months
You might also like to view...
The Secretary of the Treasury can censure, suspend, or disbar a practitioner from practice before the Internal Revenue Service for incompetence and/or disreputable conduct. Which one of the following is considered disreputable conduct?
A. Being indicted for any criminal offense under the revenue laws of the United States. B. Having your motor vehicle license suspended as a result of numerous traffic violations. C. Being indicted of any felony under federal or state law for which the conduct involved renders the practitioner unfit to practice before the Internal Revenue Service. D. Giving false or misleading information, or participating in any way in the giving of false or misleading information to the Department of the Treasury or any officer or employee thereof.
Because market share is hard to obtain, it should not be considered in a marketing audit
Indicate whether the statement is true or false