Which of these is not a critical path activity?

A professor is planning an informal gathering for 100 or so of his closest friends. The project breaks down as follows:

Activity Time Predecessor
Call planner 12 -
Book caterer 10 -
Hire quartet 9 Call planner
Schedule cleaning crew 15 Call planner
Stock wine cellar 7 Book caterer
Hire valets 8 Schedule cleaning crew, Stock wine cellar
Schedule butler overtime 13 Hire quartet, Hire valets

A) hire quartet
B) hire valets
C) schedule butler
D) schedule cleaning crew

Answer: A

Business

You might also like to view...

DAS, Inc. is preparing its financial forecast for next year and its discretionary financing needed is

negative. This means that A) the predicted change in spontaneous liabilities and retained earnings must be greater than the predicted change in total assets. B) the dividend payout ratio must be greater than the predicted growth rate in sales. C) the predicted change in total assets must be negative. D) sales growth must be negative.

Business

In the capital asset pricing model, an increase in inflationary expectations will be reflected by

A) a parallel shift downward in the security market line. B) a decrease in the slope of the security market line. C) an increase in the slope of the security market line. D) a parallel shift upward in the security market line.

Business