If the explosion of the bill of material tells MRP how much of each part is needed, how does MRP learn when each of these parts is needed?

What will be an ideal response?

Timing is established with the time-phased product structure, which turns a bill of material on its side and adds lead times for each component. Each component is then offset to accommodate lead times.