Create a resource loading table and perform resource leveling on the project composed of the activities in this table. Activities listed in the table are measured in the number of eight-hour days. The maximum amount of time used per day is 16 hours

Activity Time Predecessor
A 6 --
B 1 --
C 2 A, B
D 4 --
E 1 C, D
F 1 E
G 6 E
H 4 F
J 4 F
K 3 G, H
L 5 J, K
M 3 L

The initial resource loading table with early starts is shown below:

Day 1 is problematic, but activities B and D both have plenty of slack. Activity B has a late start of 5 and D has a late start of 4. Starting D on Day 2 changes the schedule the least and keeps the project under 16 hours per day until Day 11. Activities G, H, and J combine for 24 hours on Days 11-14; G has no slack, H has 1 day slack, and J has 4 days slack. Move J back to a Day 15 start time to resolve this constraint and the new loading table appears below:

Business

You might also like to view...

The peculiar ____ doctrine makes an employer liable for the acts of an independent contractor when the independent contractor has been engaged toperform a nondelegable duty

Fill in the blanks with correct word

Business

An appraisal is an estimate of what your home and property are worth

Indicate whether this statement is true or false.

Business