Disaggregation:

A) breaks the aggregate plan into greater detail.
B) transforms the master production schedule into an aggregate plan.
C) calculates the optimal price points for yield management.
D) converts product schedules and labor assignments to a facility-wide plan.
E) is an assumption required for the use of the transportation model in aggregate planning.

A