In the event that a buyer receives a shipment of seriously defective goods, under the CISG:
A) the buyer may accept the goods and reduce the amount paid to the seller accordingly
B) the buyer must notify the seller of the defects within a reasonable time.
C) the seller may cure the defect up until the time for performance has expired.
D) the seller may request additional time to perform even though he will be late in so doing.
E)all of the above.
E