According to the scrum essentials, when is a project said to be done?

What will be an ideal response?

Work continues in a repeating cycle of scrum periods until one of three conditions is
met:
• The customer is satisfied with the product created and decides to accept the work product, even
if some requirements are left unsatisfied.
• The project runs out of time.
• The project runs out of money.