Project managers use ________ to track progress toward completing a project

A) radial charts
B) Gantt charts
C) progress placards
D) routing paradigms
E) infographics

B
Explanation: B) A Gantt chart is essentially a series of time line charts all expressed in the same graph with a single horizontal axis expressing time within a project.