A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table. Use Newbold's model to determine the aggregated buffer of one standard deviation for this project

Activity Average Worst-Case
X 12 20
Y 20 25
Z 14 24
W 18 26
A) 31 days
B) 16 days
C) 8 days
D) 5 days

C