A project has three paths. A-B-C has a length of 25 days. A-D-C has a length of 15 days. Finally, A-E-C has a length of 20 days. Which one of the following statements is TRUE?
A) A-D-C is the critical path.
B) A-B-C has the most slack.
C) The expected duration of this project is 25 days.
D) The expected duration of this project is 25 + 15 + 20 = 60 days.
C
Business
You might also like to view...
Using language analysis software to track public opinion is an example of what?
A) Recruitment B) Sentiment analysis C) Social customer service D) Networking E) Social media complexity
Business
Fraudulent misrepresentation is:
A) a correct statement; B) an inaccurate statement that may or may not have been done intentionally C) an incorrect statement made knowingly with the intention of causing injury to another D) an incorrect statement made without the intention to cause injury to another E) a type of mistake in contract law