Which of the following statements concerning MRP is TRUE?
A) Dependent-demand items tend to experience relatively constant demand rates.
B) MRP systems use independent demands for each component item.
C) Capacity requirements planning (CRP) uses open orders (scheduled receipts) and planned order releases to estimate capacity requirements for critical workstations.
D) The most accurate way to forecast dependent demand is to examine past usage rates.
C