The jobs listed below need to be completed. Assume that it is now day 140

If the jobs are sequenced according to the shortest processing time rule, what is the average completion time?

Job Processing Time (days) Job due date (days)
A 20 180
B 30 200
C 10 175
D 16 230
E 18 210

A) 47.6 days
B) 60.2 days
C) 94.0 days
D) 2.5 days
E) 238.0 days

A

Business