The percentage-of-completion method

a. is affected by the actual schedule of cash collection.
b. cannot be used if the contract specifies that the contractor will receive the entire contract price only on completing construction.
c. measures the proportion of total work carried out during the accounting period either from engineers' estimates of the degree of completion or from the ratio of costs incurred to date to the total costs expected for the entire contract.
d. is not a method allowed by U.S. GAAP.
e. none of the above.

C

Business

You might also like to view...

Which of the following is true about the relationship of SEM to factor analysis?

A) The measurement model in SEM is similar to factor analysis in that both techniques have variables with loadings on factors. B) Concepts such as correlations and covariances are common to both the techniques. C) SEM, we have to specify which variables are associated with each construct based on theory. D) A and C are correct. E) A, B and C are correct.

Business

You have been asked to locate secondary data for your small organization's research needs. Which of the following is NOT a common source for this type of research?

A) the local chamber of commerce B) the U.S. Census Bureau C) competitors' Web sites D) online surveys E) the library

Business