What is the probability that the critical path for this project will be completed within 80 weeks?

What will be an ideal response?

Answer: 0.8413

Business

You might also like to view...

When punishing an employee, it is best to give out disciplinary action as soon as possible after the undesirable behavior.

a. true b. false

Business

What are the three questions that must be considered with regards to data communications?

A) 1. how the data are delivered, 2. how accurate the data are once delivered, and 3 . how accessible the data are to those who need to use it B) 1. how the data are received, 2. how accurate the data are once delivered, and 3 . how accessible the data are to those who need to use it C) 1. how the data are delivered, 2. how accurate the data are once received, and 3 . how accessible the data are to those who need to use it D) 1. how the data are delivered, 2. how accurate the data are once delivered, and 3 . how accessible the data are to those who sent it