Which of the following identifies the project activities that must be completed, the expected start and end dates, and what resources are assigned to each task?
a. Project schedule
b. Project milestone
c. Project deadline
d. Slack time
a. Project schedule
A project schedule identifies the project activities that must be completed, the expected start and end dates, and what resources are assigned to each task. A project schedule is needed to complete a project by a defined deadline, avoid rework, and ensure that people know what to do and when to do it.