Sam and Dave have identified 9 activities that are required to complete their next project and developed a snazzy resource loading table

Since they each work 8 hours a day, they need your help to perform resource leveling on their project such that they can finish it by the close of business on Day 24. Activity float times are indicated by bracketed cells in the table. Times indicated in the table are in hours; the top row shows the day number of the project. The total hours for each day are shown in the bottom row of the table and cannot exceed 16 hours. The total resource time in any day cannot exceed 16 hours.

Pushing activities X, T, and R back to their late start times accomplishes the objective of finishing on time and at less than 16 hours of labor each day.

Business

You might also like to view...

Becky is planning to take out a mortgage for $350,000 for 30 years at 4% compounded monthly. How much interest will she pay the bank over the life of the loan?

A) $77,045 B) $574,547 C) $924,547 D) $427,045

Business

If a manager relies on feedback control, he or she does not have to use any other type of control

Indicate whether the statement is true or false

Business