Project control should be:

A) Maintained by the project organization using the most complete measurement system, earned value management.
B) Maintained by the project organization using the simplest measurement, an S-curve.
C) Maintained by both the project organization and the customer using the most complete measurement system, earned value management.
D) Tailored to the needs and culture for which an organization intends it.

D