Swiss Furniture Company manufactures bookshelves and uses an activity-based costing system. The following information is provided for the month of May:

Activity Estimated Indirect Activity Costs Allocation Base Estimated Quantity of Allocation Base
Materials handling $6,400 Number of parts 3,200 parts
Assembling $11,200 Number of parts 3,200 parts
Packaging $2,240 Number of units 800 bookshelves

Each bookshelf consists of 4 parts. The direct materials cost per bookshelf is $30.00.

What is the cost of materials handling and assembling per bookshelf?
A) $8.00
B) $24.80
C) $22.00
D) $14.00

C
Explanation: C)
Handling $6400 / 3200 parts × 4 parts = 8.00
Assembling $11,200 / 3200 parts × 4 parts = 14.00
Total 22.00

Business

You might also like to view...

Fraud is one of the factors that prevents genuine assent

Indicate whether the statement is true or false

Business

What is the probability of 2 or fewer breakdowns?

Two hundred simulation runs were completed using the probability of a machine breakdown from the table below. The average number of breakdowns from the simulation trials was 1.93 with a standard deviation of 0.20. No. of breakdowns per week Probability Cumulative probability 0 .10 .10 1 .25 .35 2 .36 .71 3 .22 .93 4 .07 1.00 A) .25 B) .35 C) .36 D) .71

Business