Which of the following is true regarding gates in the project lifecycle?
A. Each phase has only one gate.
B. Passing a gate requires gaining some type of approval.
C. The project manager makes gate approvals for team members.
D. Gates occur at the beginning of each phase.
B. Passing a gate requires gaining some type of approval.