The critical path for the network activities shown below is ________ with duration ________

Activity Duration Immediate
Predecessors
A 2 --
B 4 --
C 6 A,B
D 1 A,B
E 2 B,C,D

A) A-D-E; 5
B) B-E; 6
C) B-D-E; 7
D) A-C-E; 10
E) B-C-E; 12

E